Blackstone Digital Infrastructure Trust’s agreement to acquire a 75 percent stake in two AWS joint ventures, in a transaction valued at around $5 billion, and AirTrunk’s proposed investment of $10.6 billion in Andhra Pradesh were this week’s largest capital developments. The former pairs infrastructure ownership with a full AWS leaseback, while the latter signals substantial expansion ambitions in India, although the memorandum of understanding is not a commitment to build.

Approvals and power availability remain important constraints: Texas accounts for 56 percent of planned US capacity in states whose governors support or have imposed approval pauses, while CDC’s expanded 1.4GW western Sydney proposal still depends on power supply. For leadership teams, the distinction between announced capacity and deliverable projects matters, with planning, grid connection and project delivery expertise central to deciding where and when to scale recruitment.

North America

  • Blackstone Digital Infrastructure Trust acquires majority stake in AWS joint venture for $5bn

    Blackstone Digital Infrastructure Trust agreed to acquire a 75 percent stake in two AWS joint ventures covering 13 newly constructed powered shells, in a transaction valued at around $5 billion and expected to close in Q4 2026. AWS will lease back the entire portfolio and retain maintenance responsibility, making its infrastructure operations and local workforce training plans more relevant to hiring leaders than the ownership change itself.

  • Giga Energy secures $1bn lease for 60MW data center in Hunt County, Texas

    Giga Energy secured a $1 billion, ten-year lease with an unnamed US AI cloud provider for 60MW at its Project Clay campus in Hunt County, Texas, with service expected in spring 2027. The project is expected to create around 300 construction jobs, with its factory-first delivery model requiring coordination between offsite manufacturing and onsite assembly teams.

  • Texas holds 56% of the US data centre capacity facing a governor's pause

    Cleanview estimates that 158.6GW of planned US data centre capacity sits in states whose governors support or have imposed approval pauses, with Texas accounting for 88.4GW, or 56% of that total. Hiring leaders face uncertainty over recruitment timing and locations for planned developments, while projects already under construction are less exposed because most pauses target new approvals.

EMEA

  • Nokia, Nscale, Skeleton, Telia, and Verda form gigafactory consortium

    Nokia, Nscale, Skeleton, Telia, and Verda formed AI Gigafactory Northern to bid for European funding to develop AI data centers across Finland, Estonia, Latvia, and Sweden. If the plans proceed, delivery will require coordinated teams spanning AI cloud platforms, network infrastructure, power systems, and data center operations across the Nordic and Baltic markets.

  • GIC and Saudi Telecom compete on Pure DC minority stake bid

    GIC, partnering with Copenhagen Infrastructure Partners, and Saudi Telecom are reportedly competing for a minority stake in Pure DC, with owner Oaktree seeking an $8 billion valuation to fund expansion. Pure DC’s plan to triple its capacity points to potential demand for development, construction and operations leaders, particularly in Europe and the Middle East.

  • 100MW data center planned in Sussex, UK

    Meridian One is proposing a 100MW data center campus in Hickstead, West Sussex, while Pace DC plans a four-building campus in Bedfordshire connected to solar generation and battery storage, with neither project yet submitted for planning permission. If approved and developed, the projects could create demand for construction, engineering and technical operations teams, including specialists in liquid cooling and renewable power integration.

APAC

  • US Clamps Down on Chip Exports to SE Asia in Wake of Nvidia Scandal

    The article reports that the US introduced licensing requirements for advanced chip exports to Singapore, Malaysia, Thailand and Indonesia, alongside restrictions on overseas data centres providing significant computing power to Chinese companies. These requirements increase the importance of export-control, customer due diligence and regulatory compliance expertise within Southeast Asian data centre teams.

  • AirTrunk Signs MOU for $11B in India Data Centres

    AirTrunk signed a memorandum of understanding with Andhra Pradesh for two data centre campuses with combined capacity of up to 1.8 gigawatts and potential investment of $10.6 billion. If the projects proceed, they would increase demand for data centre development, power infrastructure, construction and operations teams near Visakhapatnam.

  • CDC Expands Western Sydney Data Centre Proposal Almost Tenfold to 1.4GW

    CDC Data Centres has asked New South Wales planners to revise assessment requirements for its Kemps Creek proposal, expanding it from a single 144MW building to a six-building campus with 1.4GW of peak design capacity. The proposal highlights the importance of grid connection, planning and project delivery expertise for western Sydney data centre teams, with power supply a key dependency and no completion timeline disclosed.